G&T-led two-stage procurement puts FB Ellmer on second Lord's stand as Tavern works start

Gardiner & Theobald says substructure works have started on the Tavern Stand at Lord's after it led a negotiated two-stage procurement ending in a fixed-price design and build contract with FB Ellmer.

Bar chart: Additional seats from each stand redevelopment (seats). Tavern Stand: 780; Allen Stand: 190.
Chart: Consultancy Today

Substructure works have started on the redevelopment of the 1960s Tavern Stand at Lord's Cricket Ground after Marylebone Cricket Club (MCC) awarded a fixed-price lump-sum design and build contract to FB Ellmer, cost and project manager Gardiner & Theobald (G&T) said on 27 November.

G&T said it led the negotiated two-stage contractor procurement and supported MCC in finalising contract terms. FB Ellmer is already delivering the adjacent Allen Stand, and G&T said the appointment makes it the first contractor to deliver consecutive stands at the ground.

The redevelopment will add about 780 seats, taking the stand's capacity to 4,110, according to G&T. The project is the next phase of MCC's Masterplan.

Jay Neil, partner at G&T, said: "The challenge is to increase capacity for Members and spectators and provide better facilities for all users on a constrained site while maximising seating available each cricket season throughout the construction period."

The consultancy role

G&T said it is providing cost management and project management services to MCC, as it did on the Allen Stand. Its team helped develop the project brief, appoint the design team and secure planning consent, then guided the design through RIBA Stage 4 before the contractor procurement.

The consultancy will continue as cost manager, project manager and employer's agent throughout the phased delivery, it said. G&T's own project page for the Allen Stand records that it advised MCC on consultant team composition, procurement strategy and contractor selection for that scheme too, and the firm has said its relationship with Lord's and MCC spans more than 25 years.

The design

The Tavern Stand sits on a narrow site between the main outfield and St John's Wood Road, extending to the boundary wall it shares with the listed Grace Gate, G&T said. The design retains the existing steel frame and foundations and adds a new basement beneath the lower terrace, while a rear extension provides accommodation and supports a cantilevered new fourth tier of seating.

The redeveloped stand is designed to be fully accessible, with a Changing Places facility and additional hospitality spaces. Third and fourth changing rooms and a gym are intended to improve facilities for players.

WilkinsonEyre, appointed as architect for the Tavern and Allen stands in April 2023 following a design competition, has said the stands are designed to BREEAM Excellent and that the approach is estimated to save 613.7 tonnes of CO2. Westminster City Council's planning committee unanimously resolved to grant consent to the Tavern and Allen project on 16 April 2024, the practice said.

Programme and the Allen Stand

Construction will be phased around major fixtures and aims to maximise the number of safely available seats across four seasons, including temporary seating on the lower terrace in 2028, G&T said. Neil said retaining the existing structure and planning the work around the match calendar "have shaped the project from the outset".

MCC's own ground-development history page recorded an earlier intention to begin the Tavern Stand redevelopment in Autumn 2027, subject to Members' approval; G&T's announcement says substructure works are already underway.

Construction of the Allen Stand by F.B. Ellmer Ltd started on 8 September 2025, after the end of the international season, MCC said. That stand will add 190 seats, taking its capacity to 806, with full completion expected in winter 2026/27 so that it is in full use for the 2027 Ashes series. G&T's project page says the stand must be completed in May 2027 ahead of the World Test Championship and Ashes Test.

Stand Additional seats
Tavern Stand (G&T, 2026) 780
Allen Stand (MCC, 2025) 190

MCC's earlier announcements gave different combined totals for the two stands: about 1,000 in April 2023 and 1,100 in May 2024, when it also said the new stands would be completed in 2027.

Masterplan background

The Tavern and Allen stands follow two completed Masterplan phases, according to MCC's history page. The Warner Stand opened on 3 May 2017, and the WilkinsonEyre-designed Compton and Edrich stands, built from late August 2019, were completed for the 2021 season, adding 2,600 seats.

Robert Ebdon, MCC Estates Director, said in April 2023 that the Tavern and Allen stands "are much cherished by Members".

Temporary seating on the Tavern Stand's lower terrace is scheduled for the 2028 season.

Sources

  1. Gardiner & Theobald (opens in a new tab) (accessed 2026-11-27)
  2. Marylebone Cricket Club (lords.org) (opens in a new tab) (accessed 2026-11-27)
  3. Marylebone Cricket Club (lords.org) (opens in a new tab) (accessed 2026-11-27)
  4. Marylebone Cricket Club (lords.org) (opens in a new tab) (accessed 2026-11-27)
  5. Marylebone Cricket Club (lords.org) (opens in a new tab) (accessed 2026-11-27)
  6. WilkinsonEyre (opens in a new tab) (accessed 2026-11-27)
  7. Gardiner & Theobald (opens in a new tab) (accessed 2026-11-27)
  8. Gardiner & Theobald (opens in a new tab) (accessed 2026-11-27)

This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.

Get stories like this every Friday

The Consultancy Today weekly: the week's consultancy and surveying news in one email, free, and the TC Media Group monthly edition. Unsubscribe in one click.

By subscribing you agree to receive the Consultancy Today weekly and the TC Media Group monthly edition. We confirm your address first. Privacy.

More from Consultancy Today