The consultancy is acting as quantity surveyor, project manager and clerk of works for Wandle Housing Association on 220 affordable homes that Barratt London is building at Springfield Phase 2B.
Potter Raper is acting as quantity surveyor, project manager and clerk of works for Wandle Housing Association on 220 affordable homes that Barratt London is building at Springfield Phase 2B in Wandsworth, the consultancy said on 18 November.
The homes form part of the wider Springfield Village development and will be a mix of affordable rent and shared ownership, according to Potter Raper. The firm said it represents Wandle's interests through construction and handover.
Block B, which is made up of four sub-blocks, is now out of the ground. Potter Raper said all level 3 precast planks are complete on Blocks B3 and B4, while blockwork and brickwork have reached level 2 on Blocks B1 and B2.
Windows are in at ground and first floor and mechanical and electrical distribution is under way on those levels. The district heating connection is complete and no gas connection is required on site, the consultancy said.
The client-side role
Potter Raper set out how the three appointments divide. As quantity surveyor it is reviewing costs and variations on Wandle's behalf, including proposals for additional items such as blinds to the rented and shared ownership homes.
As project manager it chairs the monthly progress meetings, tracks actions across the client and Barratt London teams and leads the specification review for the rent and shared ownership homes.
As clerk of works it carries out regular inspections and reports defects to the project team so they can be put right before following trades cover them up.
Preparing for handover
All collateral warranties have been signed and accepted by Wandle, Potter Raper said, and the client and contractor teams are reviewing kitchen layouts, finishes and material selections together.
A handover tracker is being developed so that Wandle has a complete record of what has been installed in every home, and a home user guide template is being refined for residents.
On planning, wording has been agreed for several pre-occupation conditions and non-material amendments are being prepared to refine the appearance of the buildings. Items raised through the Considerate Constructors Scheme have been closed out, and show flats are being arranged for prospective shared ownership buyers.
The wider phase
Barratt London exchanged contracts to buy the Phase 2B land in September 2022, in an announcement from South West London and St George's Mental Health NHS Trust and master developer STEP, which described Phase 2B as the final development phase of the Springfield Hospital Village masterplan. Springfield Village said Barratt London submitted the Phase 2b planning application to Wandsworth Council in January 2023 for 440 apartments in four buildings and nine townhouses, with 50% affordable housing by habitable room.
Potter Raper's figure of 220 homes refers to the homes being delivered for Wandle within the phase.
The Trust said the Phase 2b scheme would secure the funding needed to complete its Estate Modernisation Programme. Sir Robert McAlpine, whose Capital Ventures arm forms STEP in a joint venture with Kajima Partnerships, said in August 2025 that the final land sale to Barratt London substantially funds the Trust's renewal of Tolworth Hospital and that earlier sales had already delivered two new mental health facilities at Springfield. It put the whole masterplan at about 1,300 homes, more than 500 of them affordable.
Ian Garlington, Better Communities Programme Director at the Trust, described "our plans to transform our estate to break mental health stigma".
Wandle traces its origins to the Merton Family Housing Trust, formed in 1967, and says its purpose is supporting people across south London who need a home. Potter Raper says it has provided multi-discipline construction consultancy for more than 50 years across eight core service areas.
The next milestone flagged by Potter Raper is Block B becoming watertight.
On the record: Potter Raper Ltd, Considerate Constructors Scheme
Sources
- Potter Raper Ltd (opens in a new tab) (accessed 2026-11-19)
- Potter Raper Ltd (opens in a new tab) (accessed 2026-11-19)
- Wandle Housing Association Ltd (opens in a new tab) (accessed 2026-11-19)
- Springfield Village (South West London and St George's Mental Health NHS Trust and master developer STEP) (opens in a new tab) (accessed 2026-11-19)
- Springfield Village (South West London and St George's Mental Health NHS Trust and master developer STEP) (opens in a new tab) (accessed 2026-11-19)
- Sir Robert McAlpine (opens in a new tab) (accessed 2026-11-19)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.